NEC3 Blog
Friday, 18 December 2015

PhD student survey on co-operation

›
Dear all, If you get chance please have a look at this survey. In the researcher's own words.... I retired last year after decades ...
Tuesday, 20 October 2015

Negotiation or competitive tendering - which is best?

›
Whilst I'm not the greatest fan of first past the post/competitive tendering, the market will at least give you a 'price'. You k...
Friday, 21 August 2015

NEC survey for use in Hydropower

›
Contacts for hydropower   Richard Patterson of Mott MacDonald and Warwick Fergusson of Transpower NZ are presenting at Hydro 2015. The ...
2 comments:
Wednesday, 5 August 2015

How important is the language we use in communicating?

›
Most NEC3 contracts require us to communicate in a form that can be 'read, copied and recorded' - see clause 13.1 of the NEC3 ECC. B...

Q. Do you issue or raise an early warning?

›
A. Neither of these. Assuming this is NEC3 ECC, clause 16.1 requires the Project Manager (PM) or the Contractor to give an early warning by ...

Q. Do you raise or instruct a compensation event?

›
A. Neither of these. The answer is that you notify a compensation event (CE). Most CE's arise (in an ECC contract) because the Project ...
1 comment:
Friday, 17 July 2015

It's good to get (NEC) accredited.......

›
With the widespread growth of the (UK) construction sector and increasing confidence confirmed in the Chancellor’s summer budget last week, ...