Negotiation or competitive tendering - which is best?
›
Whilst I'm not the greatest fan of first past the post/competitive tendering, the market will at least give you a 'price'. You k...
Friday, 21 August 2015
NEC survey for use in Hydropower
›
Contacts for hydropower Richard Patterson of Mott MacDonald and Warwick Fergusson of Transpower NZ are presenting at Hydro 2015. The ...
2 comments:
Wednesday, 5 August 2015
How important is the language we use in communicating?
›
Most NEC3 contracts require us to communicate in a form that can be 'read, copied and recorded' - see clause 13.1 of the NEC3 ECC. B...
Q. Do you issue or raise an early warning?
›
A. Neither of these. Assuming this is NEC3 ECC, clause 16.1 requires the Project Manager (PM) or the Contractor to give an early warning by ...
Q. Do you raise or instruct a compensation event?
›
A. Neither of these. The answer is that you notify a compensation event (CE). Most CE's arise (in an ECC contract) because the Project ...
1 comment:
Friday, 17 July 2015
It's good to get (NEC) accredited.......
›
With the widespread growth of the (UK) construction sector and increasing confidence confirmed in the Chancellor’s summer budget last week, ...
1 comment:
›